March 3, 2017, Volume 6, Issue 22

03/03/2017

Update: AEP filed proposed tariffs this week to implement the rates approved in the AEP Global Settlement.

AEP’s proposed tariffs, which require PUCO approval, implement the following rate changes with customers’ bills rendered after March 1, 2017. As previously explained in the summary of the AEP Global Settlement, any OMAEG members negatively affected by the rate changes will receive a one-time bill credit by April 9, 2017 to offset the increase in RSR charges.

Retail Stability Rider (RSR)

Schedule (Old Rate) ¢/kWh (New Rate) ¢/kWh
GS-1, GS-1 TOD, FL 0.34143 0.56300
GS-2, GS-2 TOD, GS TOD, GS-3, GS-4 First 833,000 kWh 0.33897 0.72504
GS-2, GS-2 TOD, GS TOD, GS-3, GS-4 kWh in Excess of 833,000 0.33897 0.08000

Phase-In Recovery Rider (PIRR) Ohio Power Rate Zone

Delivery Voltage (Old Rate) ¢/kWh (New Rate) ¢/kWh
Secondary 0.75510 0.55510
Primary 0.72890 0.52890
Subtransmission/Transmission 0.71440 0.51440

 

Top