Ohio Development Services Agency (ODSA) USF Rider Application (16-1223-EL-USF)
Update: The PUCO approved the proposed USF rider rates. All customers should see a rate reduction in their USF rider beginning with the first billing cycle of January 2017. The prior and new current USF rates are as follows:
| Prior USF Rider | New USF Rider | |||
| Company | First 833,000 Kwh | Above 833,000 Kwh | First 833,000 Kwh | Above 833,000 Kwh |
| CSP | $0.0059258 | $0.0001830 | $0.0001430 | $0.0001430 |
| OP | $0.0063895 | $0.0001681 | $0.0010772 | $0.0001681 |
| DPL | $0.0026965 | $0.0005700 | $0.0007710 | $0.0005700 |
| Duke | $0.0010965 | $0.0004690 | $0.0002896 | $0.0002896 |
| CEI | $0.0042748 | $0.0005680 | $0.0010497 | $0.0005680 |
| OE | $0.0051158 | $0.0010461 | $0.0014456 | $0.0010461 |
| TE | $0.0071340 | $0.0005610 | $0.0004615 | $0.0004615 |